Two Cable Makers Are Holding €24 Billion of the Grid's Queue

Prysmian put its transmission backlog at about €16.5 billion on 29 October 2026. Nexans reported €7.8 billion in PWR-Transmission a week earlier, mainly subsea. Between them that is roughly €24 billion of committed grid work at two listed suppliers, and both are raising or holding guidance while they spend to add capacity. When the binding constraint stops being the order and becomes the factory slot, the commercial job of every supplier underneath changes.

Montre
Réponse rapide
How much grid cable work is already committed, and what does that mean for suppliers?
On 29 October 2026 Prysmian reported that its Transmission backlog "stands at approximately €16.5 billion", with a further "approximately €2 billion" of awarded projects not yet counted in it. On 22 October 2026 Nexans reported an adjusted PWR-Transmission backlog of €7.8 billion as of 30 September 2026, up 0.7% on the end of June, and described its pipeline as strong in subsea. Taken together, two listed cable makers are carrying on the order of €24 billion of committed transmission work, before the €2 billion Prysmian has won but not yet booked. Both companies are simultaneously investing to add production capacity. For anyone selling into grid and interconnector programmes, that combination is the whole story: demand for this equipment is no longer the scarce thing. Delivery capacity is. A supplier's commercial advantage shifts from persuading a buyer that the work is needed to proving it can hold a date.
Points clés à retenir
  • Two listed suppliers hold roughly €24 billion of committed transmission work. Prysmian put Transmission at about €16.5 billion on 29 October 2026; Nexans put PWR-Transmission at €7.8 billion as of 30 September 2026.
  • The scarce input is capacity, not appetite. Prysmian raised full-year adjusted EBITDA guidance to €3,075 million to €3,125 million from €2,800 million to €2,900 million, and its Q3 adjusted EBITDA rose 32.1% on sales up 13.1% organically. Margins expanding faster than volume is what a capacity-bound supplier's accounts look like.
  • Subsea is the tight segment. Nexans described its backlog as mainly subsea-driven and said "The pipeline of activity remains strong in subsea activity." Its 2026 guidance explicitly excludes the Great Sea Interconnector, a reminder that in subsea the schedule, not the signature, decides which year revenue lands in.
  • The new money is not all going subsea. Prysmian's board approved a programme of more than €700 million that includes a second copper rod mill at McKinney, Texas, four medium-voltage production lines and more metal-clad cable capacity for data centres. Nexans is putting about €62 million into medium-voltage accessories in Europe and the United States. Both are building out the distribution and data-centre layer, not only the headline interconnector business.
  • For suppliers one tier down, the sales argument inverts. In a capacity-bound chain the buyer's question is not whether they need the equipment but whether a given supplier can be qualified and scheduled. That rewards qualification, documented lead times and framework positions over conventional demand generation.
How much work is actually committed?

Roughly €24 billion, at two companies

The clearest way to see the state of the electricity grid supply chain is not a forecast. It is the order book of the people who make the cable. Two listed companies dominate the high-voltage end of it in Europe, and both reported in the last ten days of October 2026.

Prysmian's quarterly release of 29 October 2026 is unambiguous about the scale: "As of October 29, 2026, the backlog stands at approximately €16.5 billion." The same document adds two qualifications that matter more than they look. The first: "Additional awarded projects worth approximately €2 billion have yet to be included in the backlog." The second: "The backlog now includes the contribution from Xtera." So the headline figure is both understated, by the awarded work not yet booked, and partly inorganic, by the acquisition folded into it.

Nexans reported a week earlier, on 22 October 2026, and put its adjusted PWR-Transmission backlog at €7.8 billion as of 30 September 2026, up 0.7% on 30 June 2026, and described it as mainly subsea-driven.

Add them and two suppliers are carrying on the order of €24 billion of committed transmission work, or about €26 billion once Prysmian's awarded-but-unbooked projects are counted. That is not a pipeline, a market estimate or an addressable opportunity. It is signed work with delivery dates attached, disclosed by the companies that have to deliver it.

The number is worth holding onto because of what it rules out. A backlog of that size at two firms means the question facing grid programmes is no longer whether anyone wants to buy transmission equipment. It is who can make it, and when.

An offshore heavy-lift crane vessel under way. In subsea transmission the vessel, not the order, is usually the scarce thing.Projet 54An offshore heavy-lift crane vessel under way. In subsea transmission the vessel, not the order, is usually the scarce thing.
How do you tell demand-led growth from capacity-led growth?

Look at whether margin is outrunning volume

A supplier growing because its market is growing tends to show revenue and profit moving together. A supplier growing because it is one of few able to deliver shows something different: profit moving faster than revenue, because scarcity is being priced.

Prysmian's third quarter shows the second pattern. Sales were €6,417 million against €5,030 million a year earlier, up 13.1% organically. Adjusted EBITDA was €851 million against €644 million, up 32.1%. Over nine months, sales of €17,656 million were up 9.2% organically while adjusted EBITDA of €2,182 million was up 22.9%. In both windows earnings grew at roughly two and a half times the organic sales rate.

The company then raised full-year guidance for adjusted EBITDA to a range of €3,075 million to €3,125 million, from €2,800 million to €2,900 million, and lifted its free cash flow range to €1,750 million to €1,850 million from €1,650 million to €1,750 million. Chief executive Massimo Battaini described it as "This was Prysmian's best quarter to date".

Nexans is the useful control case, because its figures are less dramatic and so show where the tightness actually sits. Third-quarter standard sales were €1,698.2 million, up 21.4% as reported but 9.0% organically, with the gap explained by acquisitions. Over nine months, standard sales of €4,946.7 million were up 10.1% reported and 3.9% organic. Its Electrification business grew 5.3% organically over nine months and 7.1% in the third quarter alone, so the rate improved as the year went on. Guidance was confirmed rather than raised: adjusted EBITDA of €770 million to €840 million and free cash flow of €235 million to €325 million.

Read side by side, the two sets of accounts say the same thing with different emphasis. Growth in this part of the chain is not coming from a broad rise in orders being won. It is coming from the fact that the orders already won can only be delivered as fast as plants and vessels allow, and that scarcity shows up as margin.

Which part of the chain is genuinely tight?

Subsea, where the schedule decides the year

Nexans is explicit that its transmission backlog is mainly subsea-driven and that "The pipeline of activity remains strong in subsea activity." That is the segment where capacity is hardest to add, because it needs more than a factory: it needs cable-laying and installation vessels, and the trained crews to run them.

The most instructive detail in the Nexans release is not a growth rate. It is an exclusion. The company's 2026 guidance is stated to exclude the Great Sea Interconnector, while including the MI line load at year-end 2026 and Republic Wire from 1 June 2026. A supplier carving a named interconnector out of its own guidance is telling investors that it does not control when that project's work will be recognised.

That is the defining characteristic of subsea transmission and the reason backlog figures in this segment behave unlike backlog elsewhere. A signed contract converts to revenue when a route is permitted, a seabed survey clears, a vessel is on station and a weather window opens. Any of those can move a quarter or a year. Nexans' backlog rising only 0.7% over a quarter, against Prysmian's much larger book, is not evidence of weak demand. It is what a book looks like when new awards and conversions to revenue are running at similar rates.

For a supplier selling into these programmes, the practical consequence is that schedule risk is the currency. The buyer above you is managing a date it cannot fully control, which makes any credible commitment to a date disproportionately valuable, and any vague one disproportionately expensive. This is the same dynamic we traced in how Hitachi Energy allocates transformer capacity et dans GE Vernova's gas turbine backlog: once a supplier is allocating rather than selling, the buyer's problem becomes access.

Where are they actually spending to add capacity?

Medium voltage and data centres, not only interconnectors

If the story were only about subsea interconnectors, the capital spending would follow the subsea plants and the vessels. It does not, entirely, and that is the most commercially useful detail in either release.

Prysmian's board approved a programme of more than €700 million whose named components are revealing: a second copper rod mill at the Encore Wire plant in McKinney, Texas, four medium-voltage production lines, and increased capacity for metal-clad cables used in data centres. Copper rod is the upstream feedstock for the company's own cable production, so a second mill is a decision about input security as much as output volume. Medium voltage and metal-clad cable are the distribution layer: the cable that connects a substation to a building, a campus or a data hall.

Nexans is making a smaller version of the same bet, putting about €62 million over the next few years into medium-voltage accessories capacity in Europe and the United States. Accessories, meaning joints and terminations, are the components that let cable be installed and connected, and they are a routine hidden constraint on a project.

So the two largest listed cable makers in Europe are adding capacity disproportionately in medium voltage and in data-centre-adjacent products. That is a statement about where they expect the next bottleneck, and it points downstream of the interconnector headlines, into the connection of large loads to the network. It is consistent with the demand picture we set out in why data centres drive gas turbine demand and with the regulatory queue described in the EU Grids Package and connection queues.

For a supplier choosing where to aim, that matters more than the €24 billion headline. The headline tells you the market is capacity-bound. The capital plans tell you which part of it the incumbents think will be short next.

What do the two order books look like next to each other?

Same signal, different scale

The figures below are taken from each company's own quarterly release. The as-of dates differ by a month, which is why the two backlog figures should be added with that caveat attached rather than treated as a single point-in-time market total.

PrysmianNexans
Release date29 October 202622 October 2026
Transmission backlogApproximately €16.5 billion, as of 29 October 2026, plus approximately €2 billion awarded and not yet included€7.8 billion adjusted PWR-Transmission, as of 30 September 2026, up 0.7% on 30 June 2026
Backlog characterNow includes the contribution from XteraMainly subsea-driven
Q3 sales€6,417 million, up 13.1% organic€1,698.2 million standard sales, up 21.4% reported and 9.0% organic
Nine-month sales€17,656 million, up 9.2% organic€4,946.7 million standard sales, up 10.1% reported and 3.9% organic
Q3 adjusted EBITDA€851 million, up 32.1%Not disclosed quarterly; full-year guidance €770 million to €840 million
Full-year guidance moveRaised: adjusted EBITDA €3,075 million to €3,125 million, from €2,800 million to €2,900 millionConfirmed: adjusted EBITDA €770 million to €840 million, excluding the Great Sea Interconnector in 2026
Named capacity investmentProgramme of more than €700 million: second copper rod mill at McKinney, Texas, four medium-voltage lines, more metal-clad cable for data centresAbout €62 million for medium-voltage accessories capacity in Europe and the United States
Committed transmission work at two listed cable makers: Prysmian approximately 16.5 billion euros as of 29 October 2026, plus approximately 2 billion euros awarded and not yet booked; Nexans 7.8 billion euros as of 30 September 2026.
What should a supplier underneath these companies actually do?

Sell schedule and eligibility, not need

Most energy B2B marketing is built for a buyer who has to be convinced that a problem is worth solving. In a capacity-bound chain that buyer does not exist. The person on the other side of the table already knows what they need, has probably already been told they cannot have it when they wanted it, and is choosing between suppliers on availability, qualification and credibility about dates.

That inverts the conventional sequence. Demand generation becomes the cheap part, because demand is already there and visible in public order books. The expensive part is being eligible, being findable in the categories a category manager filters on, and being able to evidence a lead time without hedging it into meaninglessness.

Four moves follow from the October disclosures, and all four are available to a supplier with no privileged information.

01

Read the order books of the tier above you

Prysmian and Nexans publish backlog, segment growth and named capacity programmes every quarter, free. That tells you which of your customers are capacity-constrained, in which product lines, and where they are adding plant. A supplier that can discuss a customer's own disclosed constraint is in a different conversation from one pitching a capability deck.

02

Follow the capital, not the headline

The €24 billion is in transmission, but the announced investment is weighted to medium voltage, accessories and data-centre cable. If your scope touches the distribution layer or large-load connection, the incumbents have just told you they expect that to be short. Aim there before the queue forms rather than after.

03

Make your lead time a documented commitment

In a market where a listed supplier excludes a named interconnector from its own guidance because it cannot control the schedule, a credible date is a product feature. Publish real lead times by scope, with the conditions attached. Vagueness reads as risk to a buyer who is already managing a date they cannot control.

04

Get the eligibility work done before the tender

Capacity-bound buyers shortlist from suppliers already qualified, because requalifying under time pressure is the one thing a schedule cannot absorb. Framework positions and prequalification are the access mechanism, as we set out in selling into long-term agreements et selling through EPC contractors.

What would change this picture?

Three things to watch before the full-year results

This read rests on two quarterly disclosures, and both companies report full-year figures in the early part of 2027. Three specific developments would alter the conclusion rather than merely update it.

First, backlog conversion rather than backlog size. If Prysmian's approximately €2 billion of awarded-but-unbooked work enters the backlog while the headline figure stays near €16.5 billion, revenue is being recognised at about the rate new work arrives, and the queue has stopped lengthening. That would be the first sign of the constraint easing.

Second, the margin gap. Adjusted EBITDA growing at roughly two and a half times organic sales growth is the scarcity signal. If that gap narrows while volumes hold, pricing power is normalising and the supplier's advantage shifts back toward cost.

Third, the Great Sea Interconnector. It is excluded from Nexans' 2026 guidance. Whether and when it is brought back in is a concrete, checkable indicator of how subsea schedules are actually moving, and it will be visible in the company's own reporting rather than in commentary.

None of those require inside knowledge. They are all in documents the two companies publish themselves, which is the point: in a capacity-bound supply chain the most valuable competitive intelligence available to a supplier is the quarterly reporting of its own customers. If you want help turning that reading into a position in the queue, réserver un appel stratégique.

Écoutez et emportez-le avec vous

Vous préférez le format audio ou vous avez besoin de la présentation pour une analyse interne ? Le compte rendu complet est disponible sous forme d’épisode de podcast et de diaporama téléchargeable.

0:00
Votre avis

Your biggest customer has just disclosed a record order book and a plant expansion. What is the highest-value first move?

Ask which of their constraints you could absorb
The strongest move. A customer with a record backlog and new capital approved has a named bottleneck, and it is usually in their own release. Arriving with a specific offer against a disclosed constraint is a different conversation from arriving with a capability deck.
Pitch harder, while their budget is clearly there
Understandable and usually wasted. A capacity-bound buyer is not short of suppliers wanting the work and is not deciding on enthusiasm. Budget being available does not make a slot available.
Sharpen price to win on commercials
The weakest move in this market. When a buyer's constraint is schedule, discounting buys nothing they need and gives away margin you will want when capacity loosens. Price competition returns when the queue clears, not while it is lengthening.
Check you are qualified in the right categories
Unglamorous and frequently decisive. Shortlists in a capacity-bound programme are drawn from suppliers already qualified, because requalifying under time pressure is what a schedule cannot absorb. Worth confirming before any of the above.

Questions fréquemment posées

In its quarterly release of 29 October 2026 Prysmian stated that "As of October 29, 2026, the backlog stands at approximately €16.5 billion." The same release added that "Additional awarded projects worth approximately €2 billion have yet to be included in the backlog" and that the backlog now includes the contribution from Xtera. The figure therefore excludes about €2 billion of work the company has already been awarded.

Nexans reported an adjusted PWR-Transmission backlog of €7.8 billion as of 30 September 2026 in its nine-month results published on 22 October 2026, an increase of 0.7% on 30 June 2026. The company described the backlog as mainly subsea-driven and said the pipeline of activity remains strong in subsea activity.

On the evidence of these two releases, capacity. Roughly €24 billion of transmission work is already committed across the two companies, Prysmian raised its full-year adjusted EBITDA guidance to €3,075 million to €3,125 million, and its third-quarter adjusted EBITDA grew 32.1% against organic sales growth of 13.1%. Earnings growing at well above the volume rate is characteristic of a supplier whose output is constrained rather than its demand.

The company's nine-month release states that its 2026 guidance excludes the Great Sea Interconnector, while including the MI line load at year-end 2026 and Republic Wire from 1 June 2026. It does not give a reason in that document. The practical reading is that subsea project revenue depends on permitting, survey, vessel availability and weather windows, so a supplier cannot reliably forecast which year the work is recognised in, and carving the project out avoids guiding to a date it does not control.

Prysmian's board approved a programme of more than €700 million including a second copper rod mill at the Encore Wire plant in McKinney, Texas, four medium-voltage production lines and increased capacity for metal-clad cables used in data centres. Nexans is investing about €62 million over the next few years to expand medium-voltage accessories production capacity in Europe and the United States. Both are weighted toward medium voltage and data-centre-related products rather than subsea alone.

It moves the decisive question from whether the buyer needs the equipment to whether a given supplier can be qualified and scheduled. Demand generation matters less because demand is already visible in public order books. Eligibility, correct categorisation in a buyer's supplier register, documented lead times by scope and existing framework positions matter more, because those are what a buyer managing a fixed date can actually act on.

Cela vous a-t-il été utile ?
Merci pour vos commentaires.
Le point sur la croissance énergétique

Obtenez la suite gouttelettes de renseignement

Rejoignez les leaders des secteurs de l'énergie et de l'industrie et recevez directement nos informations stratégiques en matière de marketing, de croissance par IA et d'architecture des revenus, sans superflu.

CadenceDeux fois par mois
AtteindreGolfe · Moyen-Orient et Afrique du Nord · Asie · Europe