The Bond Behind the Order: What a Buyer Is Really Asking For

A performance bond is not insurance and it is not a deposit. It is a bank's promise to pay your customer if you do not deliver, and it consumes a credit line you could have used for something else. The World Bank's own standard plant contract shows how the instrument is built — and shows that the number everyone argues about is left blank for the buyer to fill in. Siemens Energy's accounts show what the same instrument costs at scale.

يشاهد
إجابة سريعة
What is a performance bond, and why does a buyer want one?
A performance bond, or performance security, is an undertaking from a bank or surety that pays your customer an agreed sum if you fail to perform the contract. It is issued on your behalf, against your credit, and the buyer can call it without first proving a loss in court. In the World Bank's standard plant contract the contractor must provide it "within twenty-eight (28) days of the notification of contract award, provide a security for the due performance of the Contract in the amount specified in the PCC" — and the amount itself is left as a blank for the buyer to complete, which is why the percentage is a negotiation and not a market standard. The practical consequence for a supplier is that winning the order consumes balance-sheet capacity as well as factory capacity. Siemens Energy secured guarantee lines of €12 billion in December 2023, a facility reinsured by the German government, which is the scale at which this stops being paperwork and becomes a financing problem.
الوجبات الرئيسية
  • A performance bond is a payment promise from your bank to your customer, not cover for you. In the World Bank's standard plant contract it must be provided within twenty-eight (28) days of the notification of contract award.
  • The percentage is not a standard. In the World Bank document the clause reads "The amount of Performance Security, as a percentage of the Contract Price" followed by a blank line. The buyer writes the number. If you treat it as fixed you have given away the negotiation before it starts.
  • You do not get it back at delivery. Unless the contract says otherwise "the security shall be reduced by half on the date of the Operational Acceptance", and it expires 540 days after Completion or 365 days after Operational Acceptance, whichever comes first.
  • Bonding capacity is a real constraint on growth. Siemens Energy's December 2023 arrangement secured guarantee lines of €12 billion and was reinsured by the German government; it was replaced in June 2025 by a new guarantee agreement with a banking syndicate.
  • Do not confuse the bonds you issue with the ones you carry for others. Siemens Energy's Note 18 reports €188 million of maximum potential future payments across all major guarantee types at 30 September 2025 — a contingent-liability disclosure, not the size of its customer bonding.
What is a performance bond?

It is your bank's promise, not your insurance policy

A performance bond — the drafting term is usually performance security — is an undertaking given by a bank or a surety company that it will pay your customer an agreed sum of money if you fail to perform the contract. It is issued on your instruction, against your credit, and in most forms the customer can call it on a written demand rather than by first proving a loss. It protects the buyer. It costs you.

The clearest free statement of how the instrument is built sits in the World Bank's standard procurement document for plant — the Request for Bids used for design, supply and installation contracts, published in October 2017. Its General Conditions require the contractor, "within twenty-eight (28) days of the notification of contract award, provide a security for the due performance of the Contract in the amount specified in the PCC". Twenty-eight days is not long if your bank has to credit-approve a new exposure.

The same conditions require that "The Performance Security shall be denominated in the currency or currencies of the Contract". That line does more work than it looks like it does. If you are paid in one currency and bonded in another, you have taken a currency position on top of a delivery obligation, and it sits on your facility for years.

A crane barge alongside a jack-up rig at sunset.Unsplash LicenceA crane barge alongside a jack-up rig at sunset.
How much is a performance bond, as a percentage?

The number everyone quotes as standard is a blank line in the document

Ask around and you will be told ten per cent. The World Bank's own document does not say that. In the Particular Conditions the clause reads "The amount of Performance Security, as a percentage of the Contract Price" — and then stops, with a blank for the employer to fill in before the tender goes out. There is no default. The buyer chooses, and it arrives in your tender pack as though it were arithmetic rather than a position.

The one place the document does commit to a figure is much narrower: where an extended defect liability applies, "The Performance Security shall be reduced to ten percent (10%) of the value of the component covered by the extended defect liability". Ten per cent of one component's value at the tail end of a contract is a different animal from ten per cent of the whole contract price for its entire life, and the two get conflated constantly.

This matters commercially because a bond is priced on your credit, not on the project's. Two suppliers quoting the same equipment at the same price are not making the same margin if one is carrying twice the security for twice as long. If you are not costing the bond into the bid, your competitor's finance director probably is.

When do you get a performance bond back?

Not at delivery. Usually not at acceptance either

The instinct is that the security dies when the equipment arrives and works. It does not. Under the World Bank conditions, unless the contract says otherwise, "the security shall be reduced by half on the date of the Operational Acceptance" — halved, not released.

Full expiry comes later. The security becomes null and void "hundred and forty (540) days after Completion of the Facilities or three hundred and sixty five (365) days after Operational Acceptance of the Facilities, whichever occurs first". So on a contract that completes cleanly you are still carrying half the exposure for roughly a year after the customer has started using the plant, and longer if the defects liability period is extended.

Put that next to a long manufacturing lead time and the arithmetic gets uncomfortable. An order booked today with a two-year build, a year of commissioning and a year of tail can occupy your guarantee facility for four years. The order looks like growth in the backlog. On the facility it looks like a line that is no longer available for the next order.

Can a customer call a performance bond unfairly?

There is a limit written into the clause, and it is narrower than it sounds

The World Bank conditions do constrain the employer: "The Employer shall not make a claim under the Performance Security, except for amounts to which the Employer is entitled under the Contract", and the employer must indemnify the contractor against the cost of a claim it was not entitled to make.

Read that carefully. It is a promise about entitlement and a remedy after the fact. It is not a mechanism that stops the bank paying. With an on-demand instrument the money usually moves first and the argument happens afterwards, with you as the claimant rather than the defendant — a materially worse position than the one you were in the day before.

Which is why the form of the security is worth as much attention as its size. The World Bank's contract forms section offers both a bank guarantee and a conditional bank guarantee, and the Particular Conditions again leave the choice as a blank for the employer. Conditional is harder to call. It is also, predictably, the one you have to ask for.

What does bonding capacity cost a large supplier?

Siemens Energy needed a sovereign to stand behind its guarantee lines

The clearest public illustration of what this instrument costs at scale is in Siemens Energy's own consolidated accounts. In December 2023 the company entered a combined call and put option over 5% of its stake in Siemens Limited, Mumbai, India, "to secure guarantee lines of €12 billion". Its 2025 notes record what happened next: "This facility, reinsured by the German government, was replaced in June 2025 by a new guarantee agreement signed with a banking syndicate."

Twelve billion euro of guarantee lines is not borrowing. It is the capacity to issue promises — advance payment securities, performance bonds, warranty bonds — so that customers will place orders at all. A manufacturer with a full order book had to pledge an equity stake and take a sovereign reinsurance to get it. That is the clearest available evidence that in this industry bonding capacity, not demand, can be the thing that limits how much work a supplier can accept.

One distinction is worth holding onto, because it is easy to get wrong in both directions. Siemens Energy's Note 18 presents "the undiscounted amount of maximum potential future payments for major types of guarantees" and totals €188 million at 30 September 2025 against €208 million a year earlier, of which guarantees of third-party performance are €83 million against €100 million. Those are guarantees the company has issued for others — the note says they "mainly include guarantees of advance payments and performance bonds in consortium arrangements", with terms "typically… up to ten years". They are not a measure of the bonds standing behind its own customer contracts. A contingent-liability note and a guarantee facility answer different questions, and quoting one for the other will make you sound wrong to a treasurer.

Why are buyers asking for more security now?

When the scarce thing is the factory slot, security is how a buyer buys certainty

This is the engine's own commercial reading rather than a claim from either document, so take it as reasoning and not as sourcing. When equipment was easy to buy, a buyer's exposure was mostly price. When the backlog is long and the constraint is the factory slot — the position the large grid cable makers are now in, with their published transmission backlogs running years ahead of their capacity, as set out in our look at the Prysmian and Nexans order books — the buyer's exposure moves to schedule. A plant that is late is not inconvenient, it is a missed connection date and a missed revenue year.

Security is one of the few levers a buyer has against that. It cannot make your factory faster, but it can make your lateness expensive, and it can make your lateness visible to your bank. Expect the percentage in the tender pack to drift up, expect on-demand forms to be preferred to conditional ones, and expect the release schedule to be written later rather than earlier.

The supplier's answer is not to refuse. It is to price it, to put the release schedule on the table as a negotiable item alongside the percentage, and to know your own facility headroom before you decide which tenders to chase. A bid you win that you cannot bond is worse than a bid you declined.

What should a supplier do before bidding?

Four things to settle before the tender, not after the award

First, read the Particular Conditions, not the General Conditions. The general text is boilerplate; every number that costs you money — the percentage, the form of guarantee, the release points, and separately the "Applicable rate for liquidated damages" and the "Maximum deduction for liquidated damages" — is a blank that somebody filled in. Blanks are negotiable in a way that printed clauses are not.

Second, get your bank's answer before you price, not after you win. Twenty-eight days from award is the contractual clock in the World Bank form, and a credit committee does not care that you have already signed.

Third, cost the full duration, not the delivery date. Half the security surviving to 540 days after completion is a carrying cost that belongs in the bid, and most tender models stop at handover.

Fourth, treat bonding headroom as a qualification criterion you apply to yourself. Buyers already test your financial standing when they build their approved-supplier lists; the honest version of that test, applied internally, tells you which work you can actually take — the same discipline a buyer applies when it builds its prequalification register. If you want a second pair of eyes on how your security terms compare with what the rest of the market is conceding, احجز مكالمة استراتيجية and bring a recent tender pack.

استمع وخذها معك

هل تفضل الاستماع إلى التسجيل الصوتي، أم تحتاج إلى العرض التقديمي للمراجعة الداخلية؟ يتوفر العرض التقديمي الكامل كحلقة بودكاست وعرض شرائح قابل للتنزيل.

0:00
رأيك

On your last major tender, who set the performance security percentage?

الأسئلة المتكررة

No, and the difference is the whole point. Insurance pays you when something goes wrong. A performance bond pays your customer when you go wrong, and then your bank or surety looks to you for the money. It is a credit instrument issued against your balance sheet, which is why it reduces what you can borrow or bond elsewhere.

It is a convention, not a standard, and the most widely used public contract form does not set it. The World Bank's Request for Bids for plant leaves the Particular Conditions clause "The amount of Performance Security, as a percentage of the Contract Price" as a blank for the employer to complete. The one place the form does fix 10% is narrower: where an extended defect liability applies, the security is reduced to ten percent of the value of the component covered by that extended liability.

Later than most bid models assume. Under the World Bank conditions, unless the contract says otherwise, the security is reduced by half on the date of Operational Acceptance, and it expires 540 days after Completion of the Facilities or 365 days after Operational Acceptance, whichever occurs first. If the defects liability period is extended on part of the works, an additional security is required for that part.

The clause says it should not: the employer "shall not make a claim under the Performance Security, except for amounts to which the Employer is entitled under the Contract", and must indemnify the contractor for a claim it was not entitled to make. In practice that is a remedy after the money has moved rather than a block on it moving, which is why the form of the guarantee — on-demand or conditional — matters as much as the amount.

Every bond issued consumes a line your bank has approved, for as long as the bond runs. Because the bond outlives delivery, a long order book ties up guarantee capacity for years. Siemens Energy's accounts show the scale this can reach: in December 2023 it pledged an option over part of its stake in Siemens Limited, Mumbai, to secure guarantee lines of €12 billion, reinsured by the German government, and replaced that facility in June 2025 with a new guarantee agreement signed with a banking syndicate.

هل كان هذا مفيداً؟
شكراً على ملاحظاتكم.
موجز نمو الطاقة

احصل على التالي إسقاط معلومات استخباراتية

انضم إلى قادة الطاقة والصناعة واحصل على معلوماتنا التسويقية، ونمو الذكاء الاصطناعي، وهيكلة الإيرادات، مباشرة وبدون حشو.

إيقاعمرتين شهرياً
يصلالخليج · الشرق الأوسط وشمال أفريقيا · آسيا · أوروبا
لا رسائل مزعجة. يمكنك إلغاء الاشتراك في أي وقت. نقرأ جميع الردود.
✓

اسمك مدرج في القائمة

أهلاً بكم في موجز نمو الطاقة، تابعوا بريدكم الوارد للاطلاع على النشرة القادمة.

المشروع 54