The Price of Being Late, Agreed in Advance

Liquidated damages are not a penalty and not a surprise. They are a number your customer wrote into the tender pack before you priced it, a cap that protects you as much as it exposes you, and — in the standard contract the development banks use for plant — a blank line sitting next to another blank line that would have paid you a bonus for finishing early. The World Bank's own form shows how the machinery is built. Saipem's filings show where the money actually lands.

Watch
Quick answer
What are liquidated damages in an energy contract?
Liquidated damages, usually shortened to LDs, are a sum fixed in the contract before anything goes wrong, payable when a party misses a date or a performance guarantee. Saipem's own glossary puts it plainly: “LDs (Liquidated Damages) are the amount of damages predetermined in the contract that one of the contracting parties agrees to pay to the other in the event of non-compliance. This clause is beneficial for both parties, as it provides a guarantee on the maximum amount of damages that can be compensated.” The buyer does not have to prove a loss, and you do not have to argue about one. In the World Bank's standard plant contract the rate and its ceiling are both blanks the employer fills in before the tender goes out, and the ceiling does double duty: “Once the ‘Maximum’ is reached, the Employer may consider termination of the Contract.” So the number that limits your liability is the same number that ends your contract.
Key takeaways
  • LDs are predetermined damages, not a penalty, and they cut both ways. Saipem's glossary calls the clause “beneficial for both parties, as it provides a guarantee on the maximum amount of damages that can be compensated.”
  • The rate and the ceiling are blanks, not standards. The World Bank's plant contract reads “Applicable rate for liquidated damages: __________________________” and “Maximum deduction for liquidated damages:”. The buyer writes both numbers. Treating them as market practice gives away the negotiation before it starts.
  • The cap is also the trip-wire. “Once the ‘Maximum’ is reached, the Employer may consider termination of the Contract” — so the clause that bounds your downside is the clause that defines the day you lose the job.
  • Under that form, missing an interim milestone carries no damages at all: save for the delay LDs themselves, failing a date in the Time Schedule “shall not render the Contractor liable for any loss or damage thereby suffered by the Employer.” Know which of your dates carry money.
  • The same form contains an early-completion bonus — and a pre-written sentence that deletes it: “No bonus will be given for earlier Completion of the Facilities or part thereof.” If nobody asks for the blank to be filled, the deletion stands.
What are liquidated damages?

A number agreed before anyone is late

Liquidated damages are the one clause in an energy contract that prices failure in advance. Rather than leaving a late delivery to be argued about afterwards, the parties agree what lateness costs per day or per week, and that figure is what changes hands. Saipem's interim financial report for the six months to 30 June 2026 carries the definition in its own glossary: “LDs (Liquidated Damages) are the amount of damages predetermined in the contract that one of the contracting parties agrees to pay to the other in the event of non-compliance.” It then adds the half that suppliers routinely forget — “This clause is beneficial for both parties, as it provides a guarantee on the maximum amount of damages that can be compensated.”

The clearest free statement of how the machinery is actually built sits in the World Bank's Standard Procurement Document for plant — the Request for Bids used for design, supply and installation contracts, published in October 2017 and used, copied and adapted across the development-bank world. Its General Conditions open with a promise: “The Contractor guarantees that it shall attain Completion of the Facilities” … “within the Time for Completion specified in the PCC”. Miss it, and the consequence is automatic: “the Contractor shall pay to the Employer liquidated damages in the amount specified in the PCC as a percentage rate of the Contract Price”.

What makes LDs different from ordinary damages is what happens after payment. Under this form the money settles the question — “The Contractor shall have no further liability whatsoever to the Employer in respect thereof.” But paying does not buy you out of the work: the same clause says the payment “shall not in any way relieve the Contractor from any of its obligations to complete the Facilities”. You have bought off the damages, not the duty. Both things are true at once, and tender teams regularly read only the half that suits them.

Two large LNG tanks carried on a barge beside a blue gantry crane at a quay.Unsplash LicenceTwo large LNG tanks carried on a barge beside a blue gantry crane at a quay.
How much can liquidated damages cost you?

The Maximum is the only number that bounds your downside, and it is also the trip-wire

There are two numbers in a delay LD clause and most bid models only carry the first. The rate is what you pay per unit of lateness. The Maximum is where the meter stops: “The aggregate amount of such liquidated damages shall in no event exceed the amount specified as ‘Maximum’ in the PCC as a percentage rate of the Contract Price.” That ceiling is the real measure of the exposure you are taking, because a rate without a ceiling is an unbounded liability and a rate with one is a known worst case.

The sting is in the next sentence: “Once the ‘Maximum’ is reached, the Employer may consider termination of the Contract.” The ceiling therefore does two jobs at once. It caps what you can lose in damages, and it defines the moment the buyer is contractually invited to remove you from the project — at which point the damages stop being the expensive part.

Neither number is a market standard, because the standard form does not contain one. In the Particular Conditions the clause is printed as “Applicable rate for liquidated damages: __________________________”, followed by “Maximum deduction for liquidated damages:” and another blank. The employer completes both before the tender is issued, and they arrive in your pack looking like arithmetic rather than like a position somebody chose. Two suppliers quoting identical equipment at an identical price are not earning the same margin if one is carrying twice the cap for twice the duration.

Do you pay for missing an interim milestone?

Under this form, no, and it is worth knowing which of your dates carry money

Project reporting treats every date on the schedule as though it were equally binding. The contract usually does not. Under the World Bank form, delay LDs attach to Completion, and the text then closes the door on everything else: save for the liquidated damages payable under that sub-clause, failing to attain any milestone or other act or thing by a date in the Time Schedule “shall not render the Contractor liable for any loss or damage thereby suffered by the Employer”.

That is a sharper allocation than most suppliers assume they are living under, and it changes how you should argue in a progress meeting. A missed interim date under this form is a programme problem and a relationship problem; it is not, by itself, a money problem. The date that carries money is the one with the LD rate behind it.

Two cautions, and they are the engine's reading rather than a claim from the document. First, this is one form's allocation: plenty of energy contracts, and most back-to-back subcontracts written by a main contractor, do attach damages to interim dates precisely because the main contractor is exposed at Completion and wants its own protection earlier. Second, a clause that does not price a missed milestone can still make it evidence — of likely delay, of the need for acceleration, or of a remedy somewhere else in the contract. Read your own form; do not import this one's generosity.

What are performance liquidated damages?

The second kind: buying your way out of a shortfall instead of fixing it

Delay is only one of the two things LDs price. The other is performance. If the plant runs but does not hit its guaranteed output or consumption figures, the World Bank form gives the contractor a choice. Where the functional guarantees are missed but the stated minimum levels are still met, the contractor may, “at the Contractor's option, either” make the changes needed to attain them at its own cost, or “pay liquidated damages to the Employer in respect of the failure to meet the Functional” guarantees.

The sum is formulaic rather than negotiated case by case, and the formula is yet another blank: “the Contractor shall pay liquidated damages at the rate of ___________________ for every complete” … “one percent (1%) of the deficiency in the production capacity of the Facilities”, with a proportionate rate for part of a percentage point. Price per point of shortfall, agreed in advance, so that a 2% miss is a known cheque rather than an argument.

The commercially important part is what the payment unlocks. Operational Acceptance — the event most payment milestones and most bond release schedules hang on — can occur when “the Contractor has paid the liquidated damages specified in GCC Sub-Clause 28.3 hereof”, and on payment “the Project Manager shall issue the Operational Acceptance Certificate”. Performance LDs are not only a cost. They are the mechanism that lets a project that is 2% short be finished, accepted and paid for instead of staying open.

There is a floor under the option, and it is absolute. Below the minimum levels of performance there is no buying out: “the Contractor shall at its own cost make good any deficiencies until the Facilities reach any of such minimum” levels. Which is why the minimum-level line in the Functional Guarantees appendix deserves more attention in a bid review than the LD rate above it. The rate prices a shortfall; the minimum decides whether a shortfall can be priced at all.

Is there a bonus for finishing early?

There is a clause for it, and a pre-written sentence that removes it

The symmetrical half of the delay clause is real and almost nobody uses it. Under GCC 26.3, if the contractor reaches Completion early, the Employer “shall pay to the Contractor a bonus in the amount specified in the PCC”, capped by its own Maximum. The Particular Conditions carry the matching blanks: “Applicable (amount or rate) for the bonus for early Completion:” and “Maximum bonus:”.

Directly beneath them the same template offers the employer a ready-made alternative, already typed: “No bonus will be given for earlier Completion of the Facilities or part thereof.” Two lines, one of which has to be chosen. In the packs that reach suppliers, the engine's consistent observation — stated as observation, not as a claim from the document — is that the LD blanks are completed and the bonus line is the one left standing. That is a choice someone made, and a choice can be questioned at clarification stage, where questions are free.

Time relief works the same way: it exists in the text and it has to be claimed. Where the employer suspends the works, the contractor is entitled to have “the Time of Completion … extended for the period of suspension without imposition of” liquidated damages. The machinery for not paying LDs is in the contract beside the machinery for paying them. The difference is that one side runs automatically and the other runs only when somebody files the notice.

Who actually pays liquidated damages?

One tier down, and it is litigated harder than anything else in the contract

A supplier's LD exposure is usually set by a contract it has never seen. The main contractor signs a Completion date with the owner, carries the delay LDs for the whole facility, and then writes its purchase orders and subcontracts so that the exposure travels down to whoever controls each date. Saipem's own risk reporting says so from the top: the factors that drive cost and schedule include “failure to meet contractual obligations by vendors, subcontractors or joint venture partners”, and the consequence it names is “as an extreme consequence, the application of Liquidated Damages clauses by the client”.

What that looks like when it goes wrong is in the same document's litigation notes, in numbers. In the arbitration between the Omani contractor Galfar and Saipem over the Duqm refinery, “Galfar requested that Saipem be ordered to pay USD 43,478,843.56 for prolongation costs (extension of time) and variation orders not recognised by Saipem.” Saipem's answer was a counterclaim “of approximately USD 20 million consisting of liquidated damages and back charges”, later particularised in its defence as USD 5,895,657.10 “by way of liquidated damages plus interest”. By the time Galfar filed its reply “it reduced its claim to USD 41,068,953.17”.

The same shape appears in Saudi Arabia, where Saipem's local company met a claim from its counterparty NCC with a counterclaim built from back-charged remediation costs and “(ii) liquidated damages for delays”, and where by February 2025 “it specified the amount of its counterclaim in SAR 137,601,035”. Read those two disputes side by side and the pattern is unmistakable: a delay claim and a liquidated-damages counterclaim are the same argument told from opposite ends of the same programme.

Nor is the exposure limited to being late. Saipem's risk disclosure on contract management notes that “In the execution phase of EPC Lump-Sum Turnkey projects, there may be changes to the contractually agreed scope of work”, and that delays in agreeing the compensation for them “may be a source of delay in payment and cause a deterioration of project margins”. An unagreed change order and an LD clock running against the original date are the ordinary combination that turns a profitable order into a loss — which is the same reason the market has been moving away from pure lump-sum work, as selling through EPC contractors keeps demonstrating.

What should a supplier settle before bidding?

Five things, every one of them cheaper now than in arbitration

First, read the Particular Conditions, not the General Conditions. The General Conditions are boilerplate; every number that costs you money is a blank that somebody filled in, and blanks are negotiable in a way printed clauses are not.

Second, price the cap rather than the rate. The rate tells you what a bad week costs. The Maximum tells you what the whole exposure is worth, and it is the number that belongs in your risk provision and in your bid price.

Third, ask which dates carry damages. If the answer is Completion only, your interim dates are management information. If the answer is every milestone — which is common in subcontracts — you are carrying a materially different contract from the one the main contractor signed upstream.

Fourth, ask for the bonus blank to be filled in. The clause exists in the same form, the question costs nothing at clarification stage, and the worst outcome is the answer you already have.

Fifth, keep the time machinery alive from day one: notices, records and the suspension and extension provisions. The relief is in the contract, but it only arrives if it is claimed on time. Buyers already apply this kind of scrutiny to you when they build their approved-supplier lists — the discipline described in what a prequalification register decides — and the same rigour applied to your own contract terms is what separates a priced risk from a surprise. If you want a second view on how your LD rates, caps and milestone definitions compare with what the rest of the market is conceding, book a strategy call and bring a recent tender pack.

Listen & take it with you

Prefer audio, or need the deck for an internal review? The full briefing is available as a podcast episode and a downloadable slide presentation.

0:00
Your take

On your last major contract, what did you do with the liquidated damages ceiling?

Frequently asked

Commercially, no: they are damages agreed in advance instead of proved afterwards. Saipem's own glossary describes LDs as “the amount of damages predetermined in the contract that one of the contracting parties agrees to pay to the other in the event of non-compliance”, and notes that the clause “is beneficial for both parties, as it provides a guarantee on the maximum amount of damages that can be compensated.” Whether a particular clause is enforceable as drafted is a question of the governing law and one for your lawyers; what you can act on commercially is the rate, the ceiling and the dates they attach to.

There is no standard, and the most widely copied public form does not supply one. In the World Bank's Request for Bids for plant the Particular Conditions print “Applicable rate for liquidated damages: __________________________” and “Maximum deduction for liquidated damages:” as blanks for the employer to complete. The performance-side formula is the same: the contractor pays “at the rate of ___________________ for every complete” one per cent of shortfall, with the rate again left blank. Any percentage quoted to you as market standard is a convention someone is asking you to accept, not a term of the form.

For delay under this form, yes, and that is the clause's main value to a supplier: “The aggregate amount of such liquidated damages shall in no event exceed the amount specified as ‘Maximum’ in the PCC”, and once paid “The Contractor shall have no further liability whatsoever to the Employer in respect thereof.” Two qualifications matter. Payment “shall not in any way relieve the Contractor from any of its obligations to complete the Facilities”, and reaching the ceiling entitles the employer to consider terminating. A cap on damages is not a cap on consequences.

Yes. The World Bank form says it in the same breath as the cap: “Once the ‘Maximum’ is reached, the Employer may consider termination of the Contract.” That is why the ceiling is the number to model. It is not only the worst financial case, it is the point at which the commercial relationship is contractually open to being ended.

Not if the contract's time machinery is used. Where the employer suspends the works, the contractor is entitled to have “the Time of Completion … extended for the period of suspension without imposition of” liquidated damages. The relief is conditional on claiming it within the contract's notice provisions, which is why records and notices are the cheapest insurance on a project. The arbitrations in Saipem's own interim report show what the alternative costs: a prolongation claim of USD 43,478,843.56 on one side, a liquidated-damages counterclaim on the other, three years and counting.

Was this useful?
Thanks for the feedback.
The Energy Growth Brief

Get the next intelligence drop

Join energy and industrial leaders getting our marketing, AI-growth and revenue-architecture intelligence, direct, no filler.

CadenceTwice monthly
ReachGulf · MENA · Asia · Europe
No spam. Unsubscribe anytime. We read every reply.
✓

You're on the list

Welcome to The Energy Growth Brief, watch your inbox for the next dispatch.

Project 54